Case Study

Mossfinnan Bridge Replacement

Location : Kirkintilloch

Client : East Dunbartonshire Council

Contract Value : £210K

Nature of Works :

Replacement of single span masonry arch bridge with a precast reinforced concrete arch system, “FlexiArch”.

Chemcem Services :

 

  • Demolition of existing structure
  • Creation of dry working zone using two sheet pile cofferdams to allow creation of new foundations
  • Positioning of flexi arch using a 100T crane
  • Arch was backfilled with mass concrete & topped with a waterproofed structural slab & new surfacing
  • For aesthetic reasons the structure was clad in natural stone which was selected locally & cut on site, to compliment local surroundings.